Network analysis - directed networks, max-flow min-cut theorem, CPM, PERT, probabilistic network analysis - Question Bank
1. In the context of flow networks, the 'cut capacity' is the sum of capacities of edges that:
2. What is the primary goal of network analysis techniques like CPM and PERT?
3. Which of the following is a representation of dependencies between tasks where activities can have multiple predecessors and successors, and different types of relationships (FS, SS, FF, SF)?
4. In a PERT network, if the project's expected completion time is 50 days and its standard deviation is 5 days, what is the probability of completing the project within 55 days?
5. What does 'probabilistic network analysis' imply?
6. What is the variance of an activity in PERT if t_o=4, t_m=7, and t_p=16?
7. Which theorem establishes a direct relationship between the maximum flow and the minimum cut in a flow network?
8. In a directed network, an edge with capacity 5 means:
9. What is the primary limitation of the basic CPM technique?
10. The concept of 'cut' in a flow network is analogous to which project management concept?
11. If an activity has an ES of 5, an EF of 12, an LS of 7, and an LF of 14, what is its slack?
12. In PERT, if the expected time (t_e) for an activity is 10 days, optimistic time (t_o) is 6 days, and pessimistic time (t_p) is 18 days, what is the most likely time (t_m)?
13. A network diagram where activities are represented by nodes and events by arrows is known as:
14. What is the probability of completing a project by a certain date in PERT analysis based on the normal distribution?
15. In PERT, the standard deviation of the project completion time is calculated by:
16. Which of the following is a probabilistic approach to network analysis?
17. What is a 'residual graph' used for in max-flow algorithms?
18. The Ford-Fulkerson algorithm is used to find:
19. In the context of max-flow min-cut, what is a 'sink' node?
20. In the context of max-flow min-cut, what is a 'source' node?
21. What is the purpose of 'dummy activities' in AOA network diagrams?
22. An activity is on the critical path if its slack is:
23. What is the 'slack' or 'float' of an activity?
24. The Latest Start Time (LS) of an activity is calculated as:
25. The Latest Finish Time (LF) of an activity is determined by:
26. The Earliest Finish Time (EF) of an activity is calculated as:
27. The Earliest Start Time (ES) of an activity is determined by:
28. What does 'LF' stand for in CPM/PERT calculations?
29. What does 'LS' stand for in CPM/PERT calculations?
30. What does 'EF' stand for in CPM/PERT calculations?
31. What does 'ES' stand for in CPM/PERT calculations?
32. What is an 'activity' in the context of CPM and PERT?
33. What is an 'event' in the context of CPM and PERT?
34. Which of the following is an activity on an arrow (AOA) representation in network diagrams?
35. Which of the following is NOT an activity on a node (AON) representation in network diagrams?
36. What is the 'capacity' of a cut in a network?
37. In network analysis, what does a 'cut' refer to?
38. What is the formula for calculating the 'variance' (σ²) of an activity in PERT?
39. What is the formula for calculating the 'expected time' (t_e) of an activity in PERT?
40. What is the 'most likely time' (t_m) estimate in PERT?
41. What is the 'pessimistic time' (t_p) estimate in PERT?
42. What is the 'optimistic time' (t_o) estimate in PERT?
43. In PERT analysis, how many time estimates are typically used for each activity?
44. What does PERT stand for in project management?
45. What is the primary advantage of using PERT over CPM?
46. In a CPM network, what is the 'critical path'?
47. What does CPM stand for in project management?
48. Which technique is primarily used for project scheduling and management that focuses on identifying the critical path?
49. What is the fundamental principle of the Max-Flow Min-Cut Theorem?
50. In network analysis, what does a directed edge typically represent?