Operations Research — Transportation, queuing, decision theory, PERT-CPM. - Question Bank
1. The Expected Value of Perfect Information (EVPI) is the difference between:
2. In the context of the Transportation Problem, what does 'destination' refer to?
3. A system with infinite calling population, Poisson arrivals, and exponential service times, with an infinite queue capacity and a single server, is best represented by which model?
4. The project duration calculated using the critical path method (CPM) is:
5. In decision theory, 'states of nature' are:
6. Which method is an iterative procedure to find the optimal solution for the Transportation Problem once an initial feasible solution is obtained?
7. The 'waiting line' in a queuing system refers to:
8. A 'dummy activity' in CPM is used to:
9. In PERT, the variance of an activity's duration is calculated as:
10. Which decision rule is most appropriate when the decision-maker has no information about the likelihood of different states of nature occurring?
11. What does the 'rho' (ρ) represent in a queuing system, specifically for the M/M/1 model?
12. In a transportation problem, the 'stepping stone method' is used for:
13. What is the primary goal of the Minimax criterion in Decision Theory?
14. Which of the following is a limitation of PERT/CPM?
15. In decision theory, a payoff matrix shows:
16. What is the 'service rate' in a queuing system?
17. In a transportation problem, if the total supply exceeds the total demand, a dummy destination is added. What is the transportation cost associated with this dummy destination?
18. Which of the following is NOT a typical output of PERT/CPM analysis?
19. The 'earliest start time' (ES) of an activity is determined by:
20. The 'latest finish time' (LF) of an activity is determined by:
21. CPM typically uses a single, deterministic time estimate for each activity, while PERT uses probabilistic time estimates. This is a key difference.
22. PERT uses a three-time estimate (optimistic, most likely, pessimistic) to calculate the expected duration of an activity. The formula for expected duration (Te) is:
23. What is 'float' or 'slack' in PERT/CPM?
24. The 'Critical Path' in a project network is the sequence of activities that:
25. What is an 'event' in PERT/CPM?
26. In PERT/CPM, what is an 'activity'?
27. What does CPM stand for?
28. What does PERT stand for?
29. PERT and CPM are project management techniques used for:
30. Which decision criterion assumes that all states of nature are equally likely?
31. What is 'regret' or 'opportunity loss' in Decision Theory?
32. The Expected Monetary Value (EMV) criterion is used when decisions are made under conditions of:
33. What does the 'Minimax Regret' criterion aim to minimize?
34. The Maximin criterion is associated with which type of decision-maker?
35. Which decision criterion is used when a decision-maker is optimistic about the future?
36. Decision Theory deals with making decisions under conditions of:
37. What does the '1' in the M/M/1 notation represent?
38. Which queuing model assumes Poisson arrivals and exponential service times?
39. What is the 'busy period' in a queuing system?
40. Little's Law relates the average number of customers in the system (L) to the average arrival rate (λ) and the average time a customer spends in the system (W). The formula is:
41. What does 'μ' (mu) represent in queuing theory?
42. In queuing theory, what does 'λ' (lambda) typically represent?
43. Which of the following is a characteristic of a Queuing System?
44. If a Transportation Problem is unbalanced (total supply != total demand), how is it typically handled?
45. What is a 'balanced' Transportation Problem?
46. In a Transportation Problem, what does 'supply' represent?
47. The Hungarian Method is primarily used to solve which type of Operations Research problem?
48. Which method is commonly used to find an initial basic feasible solution for the Transportation Problem?
49. What is the primary objective of the Transportation Problem in Operations Research?