Standard costing and variance analysis - material and labour variances, activity based costing - Question Bank
1. If the standard mix of materials is A:B = 2:1, and actual mix used is A:B = 1:1, this would primarily affect which variance?
2. The primary goal of variance analysis is to:
3. Which of the following is a 'support-level' activity in ABC?
4. An organisation using ABC may find that low-volume, high-complexity products are:
5. An organisation using ABC may find that high-volume products are:
6. Which variance is calculated to measure the difference between the standard cost of actual output and the actual cost of materials purchased, considering both price and quantity effects?
7. The purpose of calculating both Labour Efficiency Variance and Labour Rate Variance is to:
8. The purpose of calculating both Material Usage Variance and Material Price Variance is to:
9. Which of the following is a 'unit-level' activity in ABC?
10. If a company uses Activity-Based Costing, the cost of a product is likely to be higher if it:
11. In ABC, which cost pool is typically associated with the number of times a production run is started?
12. Actual labour hours worked were 500 hours at $12/hour. Standard labour rate was $10/hour. The Labour Rate Variance is:
13. Standard quantity of material allowed for 50 units is 100 kg. Actual output was 60 units, and actual material used was 110 kg. Standard price is $2/kg. The Material Usage Variance is:
14. Standard material price is $10/kg. Actual material purchased was 200 kg at $11/kg. The Material Price Variance is:
15. Standard labour rate is $15/hour. Actual hours worked for a task were 100 hours, but standard hours allowed were 80 hours. The Labour Efficiency Variance is:
16. If standard labour hours allowed for 10 units is 5 hours, and actual output is 20 units, the standard labour hours allowed for actual output is:
17. Standard cost per unit = Standard material price × Standard material quantity per unit. If standard material price is $5/kg and standard quantity is 2 kg/unit, the standard material cost per unit is:
18. The standard quantity of material allowed for a batch of 100 units is 50 kg. If 120 units are produced, the standard quantity allowed for actual output would be:
19. Which type of variance is calculated to reconcile the difference between the standard hours allowed for actual output and the hours paid for, at the standard rate?
20. A 'batch-level' activity in ABC is an activity that is performed:
21. In ABC, overhead costs are allocated to products based on:
22. Which of the following is a potential disadvantage of Activity-Based Costing?
23. The main advantage of ABC over traditional costing is:
24. Which of the following is a common cost driver for an 'Order Processing' activity in ABC?
25. ABC is particularly useful for companies with:
26. What is a 'cost driver' in the context of Activity-Based Costing?
27. In Activity-Based Costing, costs are first traced to:
28. Activity-Based Costing (ABC) is a costing method that identifies activities in an organization and assigns the cost of each activity to all products and services according to the actual consumption by each.
29. An adverse Idle Time Variance indicates:
30. What is the formula for Idle Time Variance?
31. Idle Time Variance is a part of which other variance?
32. The total Labour Cost Variance is the sum of:
33. If the actual rate paid to labour is higher than the standard rate, the Labour Rate Variance is:
34. Which variance helps in identifying whether workers were more or less productive than expected?
35. A favorable Labour Rate Variance occurs when:
36. An adverse Labour Efficiency Variance occurs when:
37. Labour Rate Variance (LRV) measures the difference between the standard labour rate and the actual labour rate paid for the hours worked. What is the formula for LRV?
38. Labour Efficiency Variance (LEV) measures the difference between the standard hours allowed for the actual output and the actual hours worked. What is the formula for LEV?
39. Labour Cost Variance (LCV) is the difference between the standard labour cost for the actual output and the actual labour cost incurred. What is the formula for LCV?
40. Which of the following is NOT a type of labour variance?
41. The total Material Cost Variance is the sum of:
42. If the actual quantity of material used is less than the standard quantity allowed for the output, the Material Usage Variance is:
43. Which variance helps in identifying inefficiencies in the use of materials?
44. A favorable Material Usage Variance occurs when:
45. An adverse Material Price Variance occurs when:
46. Material Price Variance (MPV) measures the difference between the standard price of material and the actual price paid for the quantity purchased or used. What is the formula for MPV?
47. Material Usage Variance (MUV) measures the difference between the standard quantity of material allowed for the actual output and the actual quantity of material used. What is the formula for MUV?
48. Material Cost Variance (MCV) is the difference between the standard cost of materials for the actual output and the actual cost of materials used. What is the formula for MCV?
49. Which of the following is NOT a type of material variance?
50. What is the primary purpose of standard costing?